Work progresses on Center of Hope
Intercession City FL – ICDM director Yvan Pierre and a five-person work team from Pennsylvania travel to Bayonnais today to work on the Center of Hope construction, and will return home September 7.A team of eleven builders, eight from New Jersey and three from other areas, will join forces September 24 to October 1 to continue the Center of Hope construction.A third work team will is scheduled for October 1-8.All of these teams will be working alongside Haitian builders under the direction of the general contractor. The goal is to pour the concrete ceiling of the first floor by the end of September, and to progress from there to laying up the concrete-block walls and adding the roof.Dedication of the completed facility is scheduled for the end of January 2012 as a highlight of the Hope for…